Hammer Process Condenser Water System Upgrade

This project improved the process condenser water system in the Hammer Health Sciences Center, which feeds environmental boxes and heavy equipment rooms. We installed larger pumps and cooling towers to increase system capacity and improve redundancy, as well as allow for additional laboratory equipment to be brought online in the future.

Project Facts

Project Location: Hammer Health Sciences Center

Client: Facilities Engineering

Project Program: State of Good Repair – Infrastructure and Central Plant

Project Scope: Install pumps and cooling towers

Project Area: Hammer Health Sciences Center, 18th floor

Architect: Mitchell Giurgola Architects

MEP Engineer: AKF Engineers

Structural Engineer: Severud Associates

Commissioning Agent: Facilities Engineering

Contractors: Hellman Construction, Par Mechanical, Matrix Mechanical

Year Completed: 2016